Below are additional details regarding the process, the requirements, and the next steps:

Virtual Community Information Session

Hosted By

6:30 pm – 7:00 pm

June 6, 2024

If you are interested in learning more about this proposed tower, please register at the link below
Federal, State, and local laws and regulations are an important part of safe and responsible wireless tower siting and infrastructure build-out. Arcola is proud of our proactive approach to working with local communities and jurisdictions. Frederick County will determine if the tower meets all the County code requirements. Once staff has reviewed the application, there will be two public hearings. The first is before the County Planning Commission, and the second is before the County Board of Supervisors.
You will find the tentative process schedule below, but can check this page for frequent updates:

5/31/24

Submission of Special Use Permit (SUP) application package to Frederick County

6/6/24

Virtual Community Meeting @ 6:30 PM

7/3/24

Tentative Frederick County Planning Commission public hearing at 7pm

8/14/24

Frederick County Board of Supervisors public hearing at 7pm